Work begins with the installation of scaffoldings in the atrium and other areas. The various works will then be carried out successively:
Considerable noise pollution must be expected during all construction work. In addition, the workstations in the atrium area are not available during the entire construction period.
For quiet working, you can use the other as well as the ULB Locations Schloss und Lichtwiese. Learning Spaces
There may also be service restrictions.
Earplugs will be handed out free of charge at the Service & Information counter during the conversion period.
We apologise for the noise and inconvenience and hope for your understanding!
Current Construction Progress
planned start | expected end | done | |
Assembly of the scaffolding | 2025-08-04 | ||
Maintenance and repair of glass roof construction | 2025-09-01 | 2025-09-12 | |
Replacement of the sprinkler heads | 2025-09-01 | 2025-11-25 | |
Production of inspection flaps for sprinkler heads | 2025-09-01 | 2025-11-25 | |
Conversion of the lighting to LED | 2025-06-10 | 2025-09-29 | |
Ugrading the building radio system | 2025-08-04 | 2025-09-12 | |
Dismantling of scaffolding, cleaning | 2025-11-27 |